UNDERWATER DEMOLITION TEAM HISTORIES

WWII UDT TEAM SEVEN

 

TRAINING -

CAMP PEARY:

Men volunteered for training in demolition. The training here covered the handling of explosives, blasting tree stumps, clearing of wooded areas, and general demolition. During this period the men underwent intense and thorough physical training and conditioning program. The physical training was conducted by Marine enlisted personnel whose zeal often exceeded the requirements of training. Forced marches during any and all hours of the day or night were not too uncommon.

While still in the training stages, the men displayed marked "esprit de corps" much to the dismay of the Marine personnel. The Marines never quite succeeded in pacifying this ever-exuberant display of organizational spirit in spite of having the men run an extra mile or two after a strenuous day.

During this period while the enlisted men were undergoing their own particular trials and privations, most of the original officers of Team 7 were experiencing a mode of training euphemistically termed by the Navy as "Indoctrination" in Area "E" at Camp Peary. After a month or six weeks of the above training the officers were assigned to demolition after first "volunteering." From this point on the training of the men and officers has been identical.

FORT PIERCE:

Most of the members of Team 7 received their training in Class 5 and 5A and represent approximately half of the group that was assigned to the Pacific, the other half becoming UDT 6. While in training at Fort Pierce men and officers were organized into Naval Combat Demolition Units of one officer and five enlisted men. The training consisted of physical conditioning, rubber boat work, small boat handling, some communications work, recognition of coastal silhouettes, and night approaches to the beach, The first week of training, HELL WEEK, was primarily physical and supposed to weed out the "boys" from the "men." Problems were held during all periods of the day and night covering rubber boat work on the open sea, land portages, paddling up the mud bottom, weed choked Indian River, and when it seemed the surf was particularly high there would be a day problem over the jetties for those who survived a night problem.

Particular emphasis was placed upon handling of explosives and demolition work. Military explosives and their uses were well covered. As soon as proficiency in handling of explosives was attained, practical work on blasting of obstacles both in and out of the water was undertaken. These operations were performed both day and night using a seaward approach to the beach to be cleared.

Except for a very casual amount of swimming in connection with physical training no emphasis was placed upon what later became a major portion of the work of a UDT.

During training, no overall plan was apparent of the work and functions later performed by UDTS. The problem of approaching a beach and performance of a mission was never solved at least to the extent of a maximum survival of personnel. To illustrate, a daylight approach to obstacles within a few yards in from the beach in the water was generally in a rubber boat filled with powder with paddlers fully exposed.

About the second week in the training program the officers and men were teamed up into crews of one officer and six or seven men and operated in this way until the last week when they were reorganized into the standard units. The last week of the training program covered practical work on obstacles along beach shorelines. In general three days was devoted to daylight blasting and about the same number at night. During these operations crews operated as units of three using rubber boats to bring the powder to the obstacles and were required to detonate their powder electrically on the exact hour.

As a point of contrast to later experiences of the team it is interesting to note that the powder was taken in by rubber boats and all personnel were dressed completely in combat greens, field shoes, helmets, and heavy "Mae West" life jackets. While a plan for fire support for such a mission may have been developed at this time, this particular phase was not introduced in the briefing for the problems.

Late during the night of the last day of the pay-off course, word was received that operations were to be called off because of heavy weather. Most of the work, however, had already been performed, but at the expense of losing several rubber boats, innumerable paddles, and all but capsizing the LCVP'S.

On Easter Sunday, April 9, the westward bound units of class 5 and 5A together with certain crews of the staff that were desirous of overseas duty boarded troop trains for their journey westward - amidst sad farewells. Contrary to the advertisements of the Pullman Company in national magazines the trip was neither comfortable nor enjoyable. Somewhere along in the western states an empty coach for prisoners was added to the last section of the train. The fortunate few who could manage to get back to this coach rode across the balance of the way in some degree of luxury.

Two days after arrival in San Francisco the units boarded the aircraft carrier U.S.S. ESSEX and left the country on 16 April 1944. Pearl Harbor was reached 20 April and the units transferred to NCDT & E Base, MAUI, via a rough riding and extremely wet LCI trip in the black of night. The feeling of the passengers in the safety of the ship and its ability to weather the rough seas was not allayed by the ship's company donning life belts during the height of the storm.

MAUI:

The introduction to demolition life at Maui was marked by two particular points: (1) the rough passage over from Pearl. (2) The week prior to Team 7's arrival the mess hall had burned down. During the entire time the team was stationed here no mess hall or galley facilities were available. The food was prepared in 55 gallon G.I. trash and rubbish containers and served to both officers and men alike in the open. During the periods of heavy winds the food became liberally sprinkled with sand and dust.

The base and grounds were just being developed at this time and during the first weeks open pipe trenches for water and sewage were everywhere.

Immediately upon arrival at Maui the units were divided on practically an alphabetical basis of the officers and their attached crews into UDT's 6 and 7 respectively with Lt. (jg) (Pappy) METTIVIN as officer in charge of Team Six and Lt. (jg) A.B. ONDERDONK as officer in charge of Team Seven.

Under the direction of Lt. (jg) ONDERDONK sixteen officers and their crews totaling 80 men listed by enclosures were formed into UDT 7. At the start the team consisted entirely of CEC officers and C.B. enlisted personnel. Organization consisted of one headquarters platoon and four operating platoons, each operating platoon having three officers.

About a week after the team's arrival at Maui the team's first commanding officer, Lt. Comdr. then Lieutenant, R.F. BURKE reported aboard for temporary duty as as observer with UDT 5. Lt. Comdr. BURKE was offered and accepted the command of the team. Lt. (jg) ONDERDONK became the executive officer with Lt. (jg) ROBBINS, Lt. (jg) PHELPS, Lt. (jg) JONES, Lt. (jg) WELLS, and Lt. (jg) McCALLISTER as platoon leaders.

From the very first it was apparent the training program here was not integrated or coordinated in any way to that of Fort Pierce, Florida. In fact the general impression created by the very meager training staff at Maui, consisting of one officer and five enlisted men, was that much of the Fort Pierce training had best be forgotten. While the Maui training was intended to be specific and detailed for the needs of amphibious warfare in the Pacific, much of the basis of the training program was at complete variance and new and different from that at Fort Pierce. Major points of difference can be summed up as follows:

  • 1. Emphasis on developing strong swimmers.
  • 2. Minimizing the use of rubber boats.
  • 3. Conducting training operations in the water without life belts- a violation of a Fort Pierce order.
  • 4. Working in the water or on the beach wearing swim trunks and swim shoes as compared to the combat greens, field shoes, and helmets required at Fort Pierce.
  • 5. The use of face masks.

Most of the practical work at Maui covered coral blasting of reefs, mushroom heads, and other coral formations. A fair amount of work was done on lip and channel blasting using methods of placing powder favored by the staff which were later dropped by the team. Briefly, the method covered placing powder in a high surf and consisted in bringing an LCVP to the reef's edge and throwing two forward grapnels on the reef which were hooked into place by swimmers. By controlling the play in the forward grapnels and by skillful handling of the boat by the coxswain the LCVP was supposed to remain in position. No particular difficulty was experienced in performing this operation on the all but surfless MAUI beaches, but there is considerable doubt that this method would have been practical in a high surf. The powder was placed by the men swimming it in and putting into place without the use of any flotation de-vice. The powder handling crew in the boats would drop the twenty-four pound tetrytol pack into the hands of swimmers bobbing up and down in the sea who would then swim it in. In rough weather it was considered proper to throw a life ring over the bow and secure the ring to the reef by means of a light grapnel. The ring and line attached to the bow were to be used as a life line for swimmers.

Originally the embarkation date for combat areas was about 15 May 1944. At this date, however, the team's training was continued for another two weeks to cover an entirely new and hitherto uncalled for function - reconnaissance.

Operating jointly and oft-times competitively with Team 5 reconnaissance methods and systems were tried off the Maui beaches. Fundamentally the system developed then became the basic form of swimming reconnaissance. Briefly it consisted of using a landing craft towing a rubber boat alongside. Swimmers were dropped singly from the moving landing craft into the rubber boat and then into the water. At the same time that swimmers went over the side, weighted metal can buoys with three foot staffs and flags and bottom anchors were dropped over the side. In theory the can buoys were to be used by swimmers as range markers but actual experience at SAIPAN proved that the Japs found the buoys more effective range markers than the swimmers. This, in addition to the fact that the buoys were shot out from under us showed this idea to be impracticable.

Compared to the gear later considered essential for a reconnaissance swimmers the swimmers were bare of all gizmos and gadgets considered necessary by the various experimental departments later established. They were trunks, swim shoes, sheath knives, face mask, and carried a plexiglass slate and pencil. In the last combat operation of the team at Okinawa some of the swimmers wore swim fins and all of them were required to wear pneumatic type life belts.

While in the preliminary reconnaissance training period at Maui, it was soon evident that the results of reconnaissance were often "by guess and by gosh", inaccurate and misleading. In order to correct this a system of string reconnaissance was developed principally by Team 5 using fishing line and a light reel. By a combination of anchors and buoys, proponents of this system derived increased accuracy in their work. To the C.B. officers of Team 7, however, this method seemed awkward, inaccurate, and impractical. Although the team had some fifty miles of stout fishing line aboard ship for its first operation at Saipan, string reconnaissance was not used and has never been used except when directly ordered. For the Okinawa operation the method of reconnaissance, changed in name to "line control method", was part of the operation plan. The results of the string reconnaissance was satisfactory, but in two swimmers' cases, but no better than swimmers unaided by line and reel.

The first charts were drawn up on the back of laundry paper and were merely sketches and no attempt was made toward draftsmanship. At first there were no instruments, drawing equipment, or paper. These were procured only in time for the first operation after a great many demands by team officers.

Through the efforts and experiences of Team 7, preparation of charts was developed to a fair degree of proficiency and draftsmanship. On their return to Maui some six months after their first combat experience the team under Lt. ROBBINS set a drafting room, with but a negative amount of approval from the base officers, but with the "go ahead" sign of Comdr. KAUFMANN, the Training Officer and Lt. Comdr. BURKE, the Chief of Staff.

During the reconnaissance training periods the later elemental fact of keeping the landing craft moving at all times during the operation as well as picking up swimmers on the move was not yet apparent. For the most part, the LCPR would pull up alongside the swimmer, stop practically dead in the water, while the crew aboard would help the swimmers climb the rope ladder hung over the side. Shooting Japs at Saipan showed the error in method and introduced the practice of picking up swimmers on the run.

At no time during the training period at Maui was any work done aboard APD type of ships later used on operations. The teams operating exclusively in small landing craft. In order to acclimate teams to Naval gunfire support and shellfire, a partially simulated reconnaissance off the Kahoolawe beaches was held with teams 5, 6, and 7 operation jointly using radio communications for control. As a result of the rehearsal, the battleships U.S.S. CALIFORNIA and U.S.S. TENNESSEE worked out for the very first time, the principles of close inshore bombardment, for the support of troops.

On 30 May, 1944, three APDs converted World War I four stackers, veterans of the fighting through Guadalcanal, the U.S.S. GILMER, U.S.S. WATERS and the U.S.S. BROOKS, pulled into Maui anchorage and were boarded the same day by Teams 5, 6, and 7 respectively. The next day the ships pulled out and started the trip westward.

Unknown to most of the members of the team at this time, but known evidently to most of the seamen at Pearl, the bombardment group of which the APD's were a part, was the largest task force ever assembled in the Pacific. A stop over of a few days was made at Kwajalein Atoll.

After the ship was well underway from Kwajalein, operational plans and charts were made available to all officers and preliminary studies were developed. On entering the combat zone, charts and plans were shown to enlisted personnel for general study and specific discussion with the platoon officer.

Since the information available concerned Saipan, Tinian and other islands of the Marianas group, it was found expedient to assemble two complete sets of intelligence information concerning Saipan only and use them for reference. In studying the intelligence information, each platoon concentrated primarily on its particular beach and secondarily on the other beaches.

While the charts available were of a sufficiently large scale for the use of the team, overlays on clouded cellulose acetate showing the beach and reef in outline were made up to be used by each platoon leader while on the reconnaissance and in preparation of the rough beach chart.

During the period of travel to Saipan, daily discussion, study and briefing of each platoons function was made. In addition all gear required for the reconnaissance and blasting was prepared and made ready for use. Special effort was made to insure each platoon being operationally self-sufficient and ready at all times for duty.

While the team has some experience working under fire on practice runs at Kahoolawe, T.H., none of the personnel had any combat experience, nor had the team ever operated from an APD.

No opportunity for previous training between the ship and the team was possible while en route or while training at Maui. As a result there was a lack of perfect coordination between the two and teamwork was not very well developed at first.

At 0830 on 14 June 1944 (D-1 Day) the reconnaissance units of UDT 7 embarked in four LCPR's from the APD. Each full platoon of the team was used as a unit and assigned a particular beach to reconnoiter. UDT 7 was assigned the beaches Blue 1, Blue 2, Yellow 1 and Yellow 2 and of these Platoon 1 was assigned Yellow 3, Platoon 2 was assigned Blue 1, Platoon 3 Yellow 1 and Platoon 4, Blue 2. Each platoon of UDT 7 was directed to determine the following about it's assigned beaches:

  • (a) Determine location and extent of underwater obstacles, anti-boat mines, barriers, booms and all other obstructions which would prevent the passage of LVT'S.
  • (b) Select and mark best approaches to designated beaches through which channels could be blasted.
  • (c) Existence, height and character of coral lip at edge of reel
  • (d) Depth of water over reef and in lagoon.
  • (e) Condition of surf at edge of reef.
  • (f) Extent and types of obstacles encountered on reef and in approaches to designated beaches.
  • (g) Extent, type and size of anti-boat mines encountered.
  • (h) Extent and type of any obstacles observed on beaches proper.
  • (i) Character of seaward edge of reel
  • (j) Estimate of ability to clear desired channels.

In regards to demolition UDT 7 was ordered by the Operation Plan to do the following:

  • (a) Clear and mark at least one channel with a minimum width of at least fifty feet from the edge of the reef to each of the designated beaches to allow passage of LVT'S.
  • (b) Clear beaches of all horned scullys, jetted rails, booms, barriers, etc.
  • (c) Blast and mark at least two twenty feet wide passages per boat over lip of coral reef in order to permit passage of DUKW'S.

To insure that the maximum benefit from reconnaissance be attained it was ordered that the data obtained be disseminated to Admirals HILL, TURNER, and OLDENDORF stationed on ships U.S.S. CAMBRIA, MOROVIA, and INDIANAPOLIS respectively as soon as possible after reconnaissance.

While the beaches had been fairly easy to distinguish before disembarking, platoon leaders were given last minute instructions to rendezvous about the ship to get proper compass bearings to each beach. This information was not received and the LCPR's proceeded without guidance.

Proceeding under sporadic and poorly directed Naval gunfire support, each platoon conducted it's reconnaissance as detailed in Enclosure (A). While casualties had been suffered by some of the personnel in the LCPR's prior to leaving the craft, the reconnaissance was completed and all required information secured.

The reaction of the Japanese to our Naval fire is difficult to evaluate. At Saipan they opened up on the supporting warships with some large guns, necessitating a withdrawal to a longer range and return to former positions after knocking out the disclosed targets. Partly as a result of this, heavy enemy machine gun, sniper, and small caliber gun and mortar fire was encountered. In addition 12 barges moored alongside the pier at Blue 1 beach endangered the team with heavy and fairly accurate mortar fire. Naval air support was at this time occupied elsewhere and the little air cover provided was very poor and inefficient.

Due to the intensity of fire along Yellow 1 beach which beach had been assigned to Platoon 3, a usual reconnaissance from the LCPR was made and no swimmers were dropped in the water. On the other beaches, the reconnaissance, although under heavy fire, proceeded in accordance with the original plans. After most of the swimmers were picked up, Platoons 3 and 4 returned to the ship and Platoon 1 proceeded to pick up six swimmers who had been unable to be picked up because of a near miss which the LCPR from which they had been discharged had received, and consequently, it had returned to the ship.

In training at Maui the only tactic used in picking up a swimmer was to approach him with the craft, bring it to a stop and allow the swimmer to drag himself into a rubber boat which was provided alongside the LCPR and from there jump into the LCPR. Here it was discovered that motion of the LCPR was imminent to minimize the chances of receiving hits from the mortar shells that the Japs were dropping around the LCPR'S. Consequently a life ring with a line attached was rigged and this was thrown to a swimmer as the LCPR approached and passed him. The end of the line was held by a man in the boat and the swimmer was dragged safely into the LCPR.

A smoke screen was ordered by Lieut. BURKE just prior to this which probably helped reduce the accuracy of the enemy fire.

During the reconnaissance, Japs could be seen moving around the beach and several gun and sniper positions were apparent. By using .30 caliber machine guns mounted on the LCPR's and manned by APD gun crews, at ranges from 500 yards to 800 yards, and firing over the heads of the swimmers, the intensity of enemy fire was considerably reduced. As a result of this experience, on subsequent operations each LCPR was equipped with a bow and stern .50 caliber machine gun in addition to the 30's. Also selected team personnel were later given training in machine gunnery and provided the gunnery for later operations.

By drawing enemy fire from the beach installations and barges valuable information as to the enemy fire power was secured. Heavy Navy gunfire was later concentrated on known targets on the beach, barges, and snipers in the tree tops on D-1 Day and the morning of D-Day preparatory to the landing of the assault troops.

While all swimmers had plastic diver's slates and pencils with them to use on the reconnaissance to note information, none were used by the men because of the undesirability of stopping long enough to record what was being seen, thus minimizing the chances of being hit by the enemy.

The practice of dropping buoys in the water was used and is mentioned here and explained more fully in Enclosure (A). These buoys were dropped for the purpose of marking the seaward ends of the lanes which each swimmer was assigned to reconnoiter and also for the purpose of orientation as he progressed shoreward. However, this bit of nicety was found to be impractical for use under combat conditions and was discarded on future operations.

Radio communication between the LCPR's and the swimmers was carried out with no success on this operation but the use of SCR 536's were provided for this purpose. One swimmer for each beach, usually an officer, was provided with such a radio but found it cumbersome and impractical when evasive tactics and speed became necessary to avoid being hit by enemy fire. These SCR 536's were abandoned by the swimmers carrying them on the beaches and Saipan.

Radio communication between the LCPR's and the APD was maintained with SCR 610's. However, communications between the LCPR and the Naval Fire Support Ships was not direct on this operation which made calling of fire support from those ships very ineffective. Plans for subsequent operations by Team 7 embodied direct communications between LCPR's and fire support.

No obstacles of man made nature or mines were found on the beaches in place.

Consequently, no demolition of man made obstacles was required, however, wire, concrete, posts lying on the beach proper, an indication that the enemy had intended to make it a bit more difficult for Underwater Demolition Units at Saipan.

As noted heretofore the Operation Plan called for clearing and marking of certain channels through the reef. However, the discovery of a highly navigable natural channel, Charan Kanoa Channel, on Blue Beach 1 and upon investigating, the finding that it would serve well to get Landing Craft into the beach proper minimized the necessity for blasting channels through the reef.

As navigational aids to small craft, two buoys were placed at the mouth of Charan Kanoa Channel at 2200 on D-Day. In the morning of D plus 1 Day the Blue Beach master requested that a 100 foot channel be blasted through the reef several hundred yards to some deeper water along the beach. The previous days reconnaissance had showed however, that the water along the beach at the part selected was not navigable even for small craft and a channel would serve no useful purpose. However, it was decided that an attempt should be made and on D plus 1 night the work was performed. The details of transporting and loading the powder are set forth in Enclosure (A1). The reasons for failure to realize a true channel are several of which the following may be noted:

(a) Just prior to firing a message was received to hold the firing period until the following morning, as at that time, the front line was less than 200 yards offshore and any blasting would have endangered our own Marines...Thus after being exposed to the action of the surf overnight, it was found on firing the explosive charge the next morning that some of the Prima Cord had become wet. As a result, detonation of the powder was not complete. (b) The nature of the coral surrounding the Mariannas Islands is that of a very high density sand-cemented coral which does not lend itself to disintegration. Thus, on charging it and blasting, the result is an area of craters and free coral boulders which require further blasting or removal by earth moving equipment.

On D plus 3 morning, powder was placed in an attempt to form an LST ramp 100 yards wide and 35 yards deep. This operation was fairly successful although the ramp was rough and somewhat irregular.

Experience in blasting of coral for this operation indicate the inability to improve the face of a sloping hard coral reef for an LST ramp. While blasting is extremely effective in clearing boulders or coral beach and roughly shearing the lip off an abrupt reef any demolition on a sloping reef worn facily smooth by wind, water and tidal action, will result only in scattered craters and the formation of a coral lip that in themselves constitute obstacles unless the scattered debris is cleared by earth moving equipment.

Miscellaneous blasting of coral heads and boulders along the beaches to clear roads for LVT's and trucks along the reef top and buoying and flagging positions along the reef lip for LST approaches completed the work required of UDT 7 on the Saipan operation.

The operation of Saipan was the first in the Pacific Theater of operations which fully committed Underwater Demolition. Consequently much was learned there about the various tactics which constitutes an Underwater Demolition operation. These lessons could not have been foreseen and were not foreseen by the various training staffs to which Team 7 had been exposed.

It can be very easily seen that in order for a demolition team to conduct its work successfully with a minimum of exposure of it's personnel to enemy intimidation, the enemy must be kept in abeyance. This can be done by a fire support which closely coordinates itself with the work of a demolition team and is sympathetic toward its problems.

As a result of the Saipan operation it was found expedient to recommend and realize a fire support to, the source of which is as close to the beach as possible and one in which the use of rapid fire small caliber guns is emphasized. Further and later it was thought feasible to assign members of Under-water Demolition Teams directly to fire support ships to act as liaison between the two factions during the course of an operation and to acquaint the gunnery officers aboard these ships with the type of fire which would best serve demolition.

Things were learned too about the communication network of a demolition team in operation. The striking point here was that radio communication between the LCPR's and the fire support ships should be direct and fire calling should be familiar to all officers of a demolition team. Also it was learned that communication between swimmers and LCPR personnel was impractical and almost impossible when enemy harassing passes a certain point, so much communication was discontinued.

The use of swimmers and LCPR's was mildly revolutionized as a result of the Saipan operation. As stated heretofore in the operation of Saipan all four platoons of the teams were assigned a beach and all personnel of each platoon were assigned duty within that platoon. It later became apparent that should any one of these LCPR's become casualized by enemy fire or causes inherent in machinery, there would be no help or relief for it without imposing upon another LCPR which was busily engaged on another beach. Thus, it was felt expedient to embody in plans of future operations provisions for reserve and standby LCPR's whose sole function would be that of aiding operational LCPR's which had become immobilized. Further, swimmers were redistributed in the LCPR's in accordance with the "operational reserve" plan. It was felt that fewer swimmers would be used in an operation proper and the remaining swimmers allocated to the reserve LCPR's as reserve swimmers again in case an operational LCPR became immobilized.

It has been stated heretofore that Team 7's training at Maui involved the handling of landing craft during demolition operations in such a manners as to involve the use of 2 bow grapnels and 1 stern anchor to stay the craft while works of loading charges was in progress. This procedure is sheer folly in the presence of a hostile beach. In the Saipan operation it was apparent that immobility of landing craft was an invitation to disaster and maneuvers of LCPR's were initiated and employed by the coxswains. Such, for example, as approaching and leaving the beach in a zig-zag, picking up swimmers while in motion of a speed of up to 2200 RPM's, retreating from the beach after the swimmers had disembarked and performing figure eights at high speed until the swimmers were prepared to be retrieved.

With the necessity for this continuous speed came the need for methods of discharging and retrieving swimmers while the LCPR was moving. The use of a rubber boat tied along the seaward side of an LCPR had been initiated at Maui and was being practiced at Maui and was still being practiced, however, the problem was of getting an exhausted and scared swimmer into it while going 2200 RPM. This problem was solved by the rigging of a stiff line with two loops, one at each end, having an overall length of three feet. One loop was to be retained in the hands of a man placed in the rubber boat. The second loop was to be caught by the hands of the swimmer being retrieved. The swimmer had thus made contact with the rubber boat via the man it it and the double looped line and was pulled into it with very little difficulty.

Much was learned about the gunnery required on an LCPR being employed in an Underwater Demolition operation. On the Saipan operation the gunnery consisted of two .30 caliber machine guns mounted in the two forward machine gun mounts and a tommy gun operated by a gunner positioned between those in the ramp of the LCPR. Later operations saw the inclusion of a bow and stern .50 caliber machine gun in addition to the two .30 caliber machine guns.

All of the suggestions, recommendations, and changes made apparent by Team 7's operation on Saipan were made on future operations by that team and were incorporated into the Underwater Demolition scheme of things to become standard procedure in all Underwater Demolition operations in the Pacific. They were embodied in the training at Maui when Team 7 was sent there later to train new teams coming to the Pacific.

The interim of time between the Operation of Underwater Demolition Team 7 on Saipan and that on Tinian, It's next operation, was spent for the main part in confinement aboard the APD as it carried out it's duties of screening and picketing.

During this time and shortly after the conclusion of the work on Saipan, bangalore torpedoes which had been made a part of Team 7's gear requirement were moved ashore at Blue 2 beach and given to the Marines who, it was found, had more use and need for bangalore torpedoes than UDT.

The noteworthy occurrences involving the team in this time were:

(a) On 22 June 1944 the team was transferred from it's APD to the U.S.S. STRINGHAM (APD 6) because the former had been ordered back to the states for availability. (b) On 8 July a practice night reconnaissance was held in Magacienne Bay on the southeast shore of Saipan. (c) On 9 July a practice problem of floating powder into an enemy beach was held on the same beaches. (d) On 10 July a combat night reconnaissance was ordered and made on Yellow beaches along the northeast coast of Tinian in conjunction with a beach reconnaissance made by Company "A" of the Fifth Amphibious Reconnaissance Battalion compare their favorabilities with those of White Beach 1 & 2 also on Tinian and when being reconnoitered by UDT 6 in conjunction with Company "B" of the same battalion.

The main operation by UDT 7 on Tinian was on 23 July 1944 and was a diversionary daylight reconnaissance of a barrier reef off Red, Green, and Blue beaches for a total of 2500 yards. These beaches were just of Sunharin Town and it was thought to make the enemy believe that this was where the anticipated landings, which were to be made on the following day, would be staged.

Between the time of 20 June and 23 July but for the exception of the preparation for and performance of the work enumerated above, UDT 7 was retained aboard the APD with little else to do but eat, sleep, and amuse itself with what little recreation it's meager facilities could offer, i.e., card playing, book reading, bag punching, and sun tanning. Under such conditions the physical endurance as well as the morale of the men suffers much. An attempt was made to alleviate the former by daily P.T. aboard ship and frequent swim calls when the ship was at anchor. An attempt was made to help the latter by a hint made by Mr. BURKE that sniper patrols were being organized daily on the beach and that UDT's were not above sniping.

Details of the combat night and day reconnaissance are set forth in Enclosure B and B1 respectively. However certain points about these reconnaissances should be brought out at this time.

The night practice reconnaissance was conducted to determine the probability of a swimmer finding mines and other obstacles on a reef in complete darkness of night. The practice powder floating problem was conducted to determine the ease with which a 500 pound stack of powder would be floated into an enemy beach without detection and how it best could be floated. On both operations observers from the team were stationed on the beach equipped with binoculars to note the ease with which the APD, the LCPR's, and the swimmers could be detected. These observers were then asked to make verbal reports and recommendations to minimize possibilities of detection. These problems were conducted to acquaint the personnel with the problems facing them in the coming night combat reconnaissances on Tinian. The plans used on these night problems were those which were proposed for the actual reconnaissance.

Before embarking on the combat Recon of Yellow beaches Captain, now Major, James L. JONES, C.O. of the marine contingent and Lt. BURKE were warned not to alert the beaches and Lt. BURKE ordered that should signs of the beach having bear alerted themselves, personnel shall retire from the beach. As the swimmers on this operation were debarking from their rubber boats which had been brought in to within 500 yards from the beach several shots were heard which gave the impression that the beach had been alerted and that the enemy knew of our presence. In accordance with the orders the swim personnel returned to the rubber boats to the APD. The marine contingent, however, despite the seeming alert proceeded with no casualties. Since the mission of the marine contingent overlapped that of Team 7, the information desired was satisfactorily obtained and disseminated to interested parties. As for the shots that had been heard it was later felt that Jap construction personnel working at night to fortify the beach had set off several light charges of explosive in their work.

The plans for the diversionary reconnaissance embodied many of the recommendations developed as a result of the operation on Saipan. For this operation only three LCPR's were used as operational craft, and from each of these only swimmers were dropped. A fourth boat located a thousand yards from the reef was dispatched as a reserve and standby boat and in this were present seven standby swimmers.

The curtain of gunfire and air strikes were described as superb in accomplishing their purpose. The effectiveness of this support can be demonstrated by stating that the only enemy fire encountered was sniper fire and this, upon investigating, totaled three shots in number. Large caliber naval fire at known targets combined with steady 40 mm fire into the beach and above the water's edge effectively covered the Recon operation. The reef which was reconnoitered on this operation was of the barrier type and extended out from the beach proper from 500 to 1000 yards. Since this was only a diversionary feint, swimmers were ordered to go no closer to shore than the inner edge of the reef. One natural channel and a questionable natural small boat channel presented themselves on aerial photographs and maps. Certain swimmers were designated to investigate the former for it's navigability and freeness of obstructions and mines and the latter for its questionable being. This channel was not found and proved to be a misinterpretation of the photographs.

The reef was found to be a flat, relatively smooth top reef which would present no obstruction to passage of LVT's or DUKW's. No obstacles or mines were found after 45 minutes of reconnoitering by the swimmers. The recon was concluded with no casualties.

The post assault work of UDT 7 commenced on D-Day. A thorough search for anti-boat mines off the fringing reefs on Beaches White 1 and 2 was made. No mines were found, but unexploded rockets and bombs were removed to the beach. Personnel encountered enemy machine gun fire but no casualties were incurred.

On D plus 1 and D plus 2 pontoon were placed on White 1 and White 2. This team aided in the placing of these pontoons and some demolition on the beach was necessary. Due to the conditions of the reef and the approaches to the beach, a minimum amount of blasting was necessary.

The work at Tinian completed, UDT 7 began dreaming about coming back to the states. A transfer of personnel from Team 7 and the U.S.S STRINGHAM to Team 5 and the U.S.S. GILMER was made at this time since it was rather definite that the latters were returning to Maui. The following were those who were more fortunate than those who remained with Team 7:

  • Ensign Edgar O. McALLISTER, Plat. Ldr. Plat. 4
  • Carp. James R. HARRIS, Boat Officer, Plat. 3
  • Carp. Clyde V. HIGEL, Asst. Plat. Ldr. Plat. 4
  • W.M. ARNOLD, EM2c, Plat. 4
  • H. BRONSARD, RM2c
  • D.A. LEARY, CPhM
  • G.E. MUELLER, SF3c Plat. 1
  • C.R. ROSS, GM2c, Plat. 4
  • E.J. SCHLAISSER, GM1c

At this time Lt. (jg) John SCHANTZ, CEC, USNR came into Team 7 to replace Ens. Edgar O. McALLISTER as platoon leader of platoon 4 who was transferred to Team 5. No replacements were made for Carpenters HARRIS and HIGEL. Chief A.W. DENNY came to replace Chief LEARY. K.C. HOWARD was also added to the team.

The U.S.S. STRINGHAM with Team 7 aboard departed the Marianas Islands with Espiritus Santos as the objective. The two events which marked this trip were the initiation of all members of UDT 7 into King Neptune's order of the Shell-backs and the several hours we spent motionless in the water as the fuel system of the ship was being cleared of water which had found its way into the fuel oil. However, Espiritus Santos was reached with little damage either to the ship or the personnel aboard despite the rotten salmon served on the day of our initiation.

The stop at Espiritus was short, however, the team left it not on the U.S.S. STRINGHAM but on the U.S.S. ELMORE (APA 42) taking only personal gear. This transfer was made on 21 August 1944 and on the eve of that day Team 7 was on its way to the Solomon Islands. The seeming endlessness of room on an APA after having lived aboard an APD for two months was an often remarked subject among the members of Team 7.

The route of arriving at the final destination, Turner City and Florida Island, was a rather circuitous one for the ELMORE proceeded right past it and came to a stop at Russell Island on 23 August, several miles west of Florida Island. It was there that Team 7 disembarked for one night, only to reembark again the following morning on an LCT which proceeded back to Guadalcanal. There Team 7 disembarked into two LCM's which proceeded 22 miles across the strait to Turner City and Florida, arriving in the dark of the night of 24 August.

The enlisted men will long remember their first night in Turner City sleeping in a mediocrity cleared swamp in hastily prepared net-less tents. They will also remember their stay here because of the suffering their appetites underwent and the introduction to tooba juice. If it had not been for the resources of one Mims BOWEN, who always managed to have a store house of food in his sea bag, life would have been impossible there.

The reason for Team 7's presence in Turner City was reconditioning for the coming operation of the island of Pelelieu of the Palau group in the Western Carolines. However, reconditioning was a slow and painful realization in a climate that was tropical, hot and muggy, when the only time over exertion would not leave a person as limp as a rag was a couple of hours in the morning, where sleeves had to be rolled down and shirt collars buttoned at dusk to minimize the area vulnerable to an anopheles, where the water was so full of fungi that to subject a person to it for any time would have incapacitated him for the coming operation. So the best way that reconditioning could be realized was to do nothing in the way of reconditioning. Recreation was found on a nearby island after traveling two hours in an LCVP.

While at Turner City a dispatch was received by the team C.O. to dispatch six men and an officer back to Maui for the purpose of forming nuclei for new demolition teams. Lieut. BURKE asked for a volunteer officer of which there were none. Ens. DESMOND, formerly of Team 6 was immediately made a member of Team 7 and designated as the officer to return. With him went six men authentically from Team 7. They were as follows:

  • POTTER, H.F. GM1c
  • RIGGINS, R.E. CSF
  • DAVISON, W. MM2c
  • WISECUP, J.R. S1c
  • MONDONARO, J.E. GM2c
  • REED, I. GM2c

No replacements for these men were taken.

Ten long days were spent here and on 6 September Team 7 once again boarded the U.S.S. STRINGHAM which had come there from Espiritu Santos where it had left it.

On the following day the STRINGHAM shoved off with Manus Island as the objective where the staging of the Task Force which was to invade Pelelieu Island was taking place. The stay at Manus was short and uneventful, with the exception of the joining of the huge task force of which we were a part.

The Operation Plan which was to be used in the invasion of Palau was made available to the team while it was still in Turner City. Hydrographic charts of the water surrounding Pelelieu and maps of the island itself were also made available at this time. Aerial photographs of the beaches were not available at this time but were promised at a later date and before the invasion.

The time from the sailing of the ship from Turner City to its arrival off White beaches at Pelelieu on 12 September was spent by the personnel of Team 7 in preparation for the coming operation. All officers were required to read the Operation Plan and to study the charts and pictures of the beaches.

Endless conferences between Lieut. BURKE as C.O. and team officers, between the team C.O. and the ship C.O., between the officers of the team themselves were held.

Numerous briefing periods of the team officers by the C.O. of the men by the C.O. and of the men by their officers were held.

The foregoing operations were conducted both for reconnaissance and the demolition but especially for the former at this time, since that was more imminent. Intelligence and photo interpretation had reported the presence of obstacles on the beaches but before detailed plans could be laid for their demolition reconnaissance was necessary.

Details of the reconnaissance are set forth in Enclosure (C) but it is believed that certain points concerning it should be brought out at this point.

The hour at which the team would operate was not known until one hour previous to it's being committed. At about 0600 the U.S.S. NOA (APD) transporting UDT ABLE to operate in sight was sinking because of a ramming dead astern which it had received from the DD SHAW when it had veered over into the destroyer's path. Thus two destroyers and the U.S.S. STRINGHAM were ordered to rendezvous around it to screen it from subs while personnel of the SHAW were transferring to three of the ship's LCPR's. Consequently the original time for the recon was discarded and word was received that Team 7 would not be committed until that afternoon. However, at about 0900 orders were received to proceed with recon as soon as possible and at 1100 three LCPR's were lowered from the STRINGHAM to make reconnaissance.

The fourth LCPR of the ship which was intended to be used became unusable when, as it was being lowered by the ship's davits into the water, the ship's sea painter became fouled in the boat's screw and attempts to extricate the line proved unsuccessful. Consequently, last minute changes had to be made.

Fortunately, the beach to be reconnoitered required only twelve swimmers which were to be dropped by only one LCPR so that this last minute change necessitated only the elimination of an LCPR whose sole function was to have been to pick up swimmers returning from the beach.

This reconnaissance was planned embodying the idea of using as few swimmers as possible of providing for standby and reserve LCPR's and swimmers, of using direct communication between LCPR's and fire support ships, of maintaining constant mobility of LCPR's and of using .50 caliber machine guns to supplement the thirties.

The results of the reconnaissance were recorded on an outline overlay which had been previously prepared and showed range markers, steel tripods, and rows of wooden posts 75 yards from the beach were present on the reef. It was further noted that all of these had been in place for a long time as they were rusted and decayed and from all appearances formed no obstacles to landing vehicles.

The reef was smooth and flat with a gentle slope to the beach. Log barriers and concrete cubes were seen on the beach about thirty yards above the high water mark. The pill boxes observed had been demolished by naval gun-fire.

This reconnaissance was made at a time when the tide was low and the reef awash for 100 yards from the beach. There was no water to provide cover for the swimmers over much of the reef and this limited the area which could be investigated. Consequently, it was to be recommended that wherever possible reconnaissances should be conducted at high tide or as close to this stage of tide as possible. Such a stage of tide will provide more cover for the swimmers and allow them to approach much closer to the beach.

As stated heretofore it was believed that the obstacles on the reef, were no hazard to landing vehicles, however it was decided that they should be removed. This operation of demolition was planned for the following night (D minus 2) 13 September 1944, but was not actually performed until the night of (D minus 1), 14 September 1944.

The delay in the demolition was caused by the fact that the STRINGHAM was ordered to tow the three LCPR's salvaged from the APD NOA some 75 miles to Kassal Passage which was at that time under the process of being cleared of mines by minesweeps and destroyers in anticipation of using it for the fleet anchorage in the Palau's. The ship returned to Pelelieu at too late an hour to initiate the demolition mission of Team 7.

However, in accordance with the new plan, demolition of obstacles was performed on White 1 & 2 beaches at Pelelieu on D minus 1 night. This work committed three LCPR's and Boat Crews and four officered demolition crews to attach single blocks of tetrytol which had been previously rigged with readily attaching fixtures to the obstacles and demolish them.

Details of this operation are set forth in enclosure (C1) but it should be stated here that because of poor planning coupled with the fact that an over excessive number of personnel was employed and the impossibility of coordination in the darkness of night, the operation was one characterized by con-fusion and uncertainty. Although some obstacles were loaded and blown the expected ends were not realized. This operation exemplified the extreme disadvantages encountered in night work. The removed obstacles were noted on the previously mentioned prepared charts.

On D-Day morning at 0600 three team officers were dispatched with the charts showing the condition of the beaches at that time. One officer was sent to the Commander Pelelieu Transport Group, one to the White beach control vessel, and the third to report to the control vessel of the Division Beach-master. However, the APD STRINGHAM had disembarked these at such a great distance from the beaches where these ships were located that three assault waves had passed the line of the control boat or the line of departure before the data was made available to the control. The data the demolition teams accumulate is of no practical value unless provisions are made to make it available to the assault wave commanders before they are committed. Thus it was recommended that this be done even if UDT's had to operate as many as four and five days before the day of invasion.

At 1030 on D-Day one LCPR with personnel and explosives aboard prepared to do necessary demolition was sent in to the beach to stand by for orders from the beachmaster. This was done by Platoon 1 officered by Lt. (jg) ROBBINS and Ensign MILLNER.

At 1130 on D Day, Carpenter R.F. WELLS was called upon to assist in laying anchorage buoys for fuel and crane barges.

At 0600 on D plus 1 Day Carp. R.F. WELLS again reported to the Senior Beachmaster and assisted in completing the laying of anchorage buoys.

At 0600 on D plus 2 Day the beachmaster was contacted again but no work for Team 7 was requested.

At 0900 on D plus 3 a reconnaissance was conducted on beach Orange 3 for anti-tank mines as the erection of a pontoon causeway was proposed at this site. The reef was awash and the reconnaissance resolved itself into walking over it and looking for the mines. This work was done by Platoon 3 officered by Lt.(jg) ONDERDONK and Ensigns C.E. JONES and CLARK WAKEFIELD.

Further work at this site was the demolition of boulders which were too large to be moved as they were by a bulldozer.

The remainder of the post assault work performed by Team 7 at Pelelieu was concentrated at the southwest side of the island on Scarlet beaches 1,2, and 3 and 200 yards of Purple beach. Here reconnaissances were conducted in post assault fashion with no fire support since the beaches were supposedly neutralized. However, recons were necessary to investigate for obstacles and mines.

The first recon was conducted on the afternoon of D plus 3 at 1500. The beachmaster had reported the beaches secured and had ordered a reconnaissance of Scarlet 3 beach. This reconnaissance was performed by Platoons 1 & 2 officered by Lt.(jg) Sidney ROBBINS an Ens. MILLNER, Lieut. BURKE, and Ensigns R.M. PHELPS and Fay RAYMON. This beach was found to be highly defended by man made obstacles and J-13 anti-tank mines. The obstacles found here consisted of embedded steel and concrete rails and steel tetrahedrons along seaward edge of reef. The steel rails were twenty pound light gauge railroad rails and planted about 5 feet high. The concrete rails were about 6" x 6" x 5' and reinforced with steel. The tetrahedron were about 7' x 7' and made of light weight pipe or reinforcing bars.

A row of 39 J-13 mines about 100 yards in from the seaward obstacles was found. Enclosure (c) is a chart prepared from this reconnaissance.

Some low strung barbed wire entanglements and wood pickets along the edge of the beach proper with some J-13 mines were found. The reef was found to be flat with only scattered coral heads.

Demolition of most of the mines was accomplished by Platoons 1 & 2 that afternoon. The first method adopted was to carry them in a rubber boat out to sea and drop them overboard. This caused the mines to detonate when they reach a depth great enough to break the horns and glass acid vile. The second method was to gather up all the mines into one pile and load it with tetrytol and blow them up. In this way most of the mines were demolished.

On the following day platoons 3 & 4 officered by Lt.(jg) SCHANTZ and Ensign John D. TURCI and Ensign C.E. JONES and CLARK WAKEFIELD were dispatched to complete the clearing of the entire reef of obstacles and mines.

A reconnaissance was conducted to determine what remained to be cleared and it was found that all the obstacles were still intact and a few of the mines remained unexploded. These were divided between platoons 3 & 4, loaded and demolished.

On D plus 5 Day all platoons were dispatched to demolish the obstacles and mines known to be present on Scarlet beaches 1 & 2. A reconnaissance revealed that the obstacles along the seaward edge of reef consisted of 6"x6"x5' concrete rails about fifteen feet on centers with barbed and plain wire between, wood tetrahedrons filled with rocks built around every third or fourth rail. A row of 29 mines about 100 yards in from seaward obstacles was found. A few scattered "Tape Measure" anti tank mines were found among the concrete rails. Platoon 1 was detailed to demolish the obstacles on Scarlet 2 beach; platoon 2 to demolish the obstacles on Scarlet 1 beach and Platoons 3 & 4 were detailed to demolish the existing mines.

Much powder was required to demolish these obstacles because of the sturdiness of them. Enclosure (C) is a detailed explanation and drawing of these obstacles and consultation of that enclosure will convince the reader of the necessity of loading heavily in order to completely demolish. Full haversacks of tetrytol were used on the single-element obstacles. Several full haversacks of tetrytol were used on the coral packed multiple element obstacles.

In the morning Platoon 1 started loading from the north end of Scarlet Beach 2 and Platoon 2 started loading from the south end of Scarlet Beach 1. At noon when it came time for all hands to return to the ship for chow these charges were detonated. In the afternoon Platoon 1 started loading from the north end of the remaining line of obstacle and Platoon 2 from the south end meeting in the center of the line of obstacles and tying the two charges together to require only one shot. The shot was detonated and was completely successful in demolishing all obstacles.

In the meantime Platoons 3 & 4 had been charging the J-13 mines with single blocks of tetrytol by tying them to the horns of the mines with marlin and into a Prima Cord trunk line. This charge was detonated but to the surprise of all concerned, the majority of the mines remained intact. Upon investigating it was found that the mines inexplicably had not been armed and consequently the rupture of the glass acid vile in the horns had meant nothing toward detonation of the mine. The force of a single block of tetrytol had not been sufficient to detonate the charge of the mines sympathetically.

It was decided to return the following morning to subject each mine to the force of a full haversack of tetrytol and trust that the mines would be detonated sympathetically from such a force. Platoon 4 was dispatched to do this work and was successful in clearing the reef of all mines.

On D plus 6 at 0800 Platoon 2 officered by Ens. PHELPS was dispatched to make a reconnaissance of the southern extremity of Purple beach for a distance of 200 yards. This reconnaissance disclosed the presence of three rows of obstacles paralleling the beach, and just off the beach proper. The first of these rows and to seaward was of reinforced concrete posts; the second and shoreward of the first was of steel rails and the third and along the water mark was of wood log. This data in the form of a print was recorded and is set forth in Enclosure C4.

On this same day at 1400 platoon 3 was dispatched to clear the reconnoitered area of Purple beach of the obstacles found. This was done by loading each obstacle with single blocks of tetrytol and circuiting these with a single Prima Cord trunk line. The shot was fired and the demolition was successful in clearing the entire area of obstacles.

Thus on D plus 6 or 21 September 1944, Team 7 concluded it's duties on the island of Pelelieu and it's personnel were visualizing the San Francisco Bay bridge.

On the following day the APD STRINGHAM with Team 7 got underway with Manus once again as it's objective and when arriving there the grand news that our next objective was to be Pearl Harbor was received.

The task of transferring Team 7's powder from the hold of the USS STRINGHAM to that of the USS CLEMSON (APD), which was transporting UDT 6 was performed since Team 7 had no further need for it's powder. This was an all day job and to facilitate the work the two ships were closed to each other. The work progressed as the day waned into night and at about 1900 a blaze was seen enveloping the fantails of the two ships. Explosives were still in the process of being transferred and the fear that an explosion was imminent in the minds of all. The wind was from the USS CLEMSON onto the USS STRINGHAM that night, consequently the blaze which supposedly started on the former was soon spreading to the latter and doing devastating progress with burning rubber boats, SCR 610 radios, and the stacks of tetrytol which were on the deck.

Fortunately, those men who had been engaged in handling the explosives had the presence of mind to quickly throw all loose tetrytol over the side and the ship's engineer enough to suggest cutting the lines which held the two ships to each other, thus allowing them to separate.

The fire fighting ships and craft stationed in the vicinity and the ship's company personnel were quickly organized to subdue it. Landing craft from all directions came to the aid of personnel evacuation.

The fire was completely subdued before it found it's way to the depth charges or the gasoline tanks of the LCPR's, some of which were in their davits or the explosives which were being transferred. The source of the fire is not determinable but the most satisfactory explanation is that a cigarette butt had been thrown to the deck and not completely stomped out, thus igniting granules of the explosive being handled which had been left on the deck during the transfer.

The following day the STRINGHAM got underway regardless of the fire the night before and Team 7 was Pearl Harbor bound, and on the morning of 14 August 1944 Pearl Harbor was a reality.

Team 7's ultimate destination, however, was not Pearl Harbor but Maui, and the Naval Combat Demolition and Experimental Base at Kameole. Transporting was not immediately available for the team, consequently a night's lay-over at Pearl was necessary. Early the following morning a transfer was made from the STRINGHAM, which was to proceed to the states, to an LCI which would proceed with the team to Maui. Thus once again as eight months before, Team 7 found itself aboard an LCI proceeding from Pearl Harbor to Maui. This second trip was made in the daytime, however, which far outmoded the first trip at night.

Maui was reached late in the day of 15 October and after much confusion with transference of gear and personnel from the LCI to the base via LCVP's and trucks the night was spent in making our presence on the base known.

After a ten day leave the limits of which was the islands, Team 7 personnel was commandeered by the training department for training of new teams coming to Maui from Fort Pierce.

Much had been done at the base since Team 7 had left it on 1 May 1944 to improve it as a training base. The living conditions with respect to quarters for men and officers were much improved, messing facilities were apparent although yet not ready for an influx of new teams, recreation facilities were being developed, but transportation facilities were still as scant as ever.

The training department had also grown into a mentionable thing. Under the supervision of Lt. Comdr, now Comdr. D.L. KAUFFMAN, a vast training program was being initiated. APD's had been made available for training purposes as were LCPR's. Beaches were being designated along the coast of Maui which would be used to conduct simulated demolition maneuvers. Obstacles and mines were being planted on these beaches, thus presenting conditions as close as possible to factual enemy beaches.

An experimental department was being started under the immediate direction of Lt.(jg) Edgar O. McALLISTER whose sympathies were with problems which were closely associated with the demolition work. Heretofore, all experimental departments connected with demolition had interests lying in methods and equipment which were theoretical and hypothetical and were not being used by demolition units in the field and probably never would.

A mapping and photography department was being initiated but like all other departments, was still in a very embryonic stage. The thoughts for this elaborate and comprehensive training program were to be made an actuality by the personnel of Team 7.

The officers of Team 7 were assigned the various duties purporting to developing a training schedule which would bring to the new teams a thorough understanding of a combat reconnaissance and demolition operation.

Lieut. now Lt. Comdr. R.F. BURKE was made Training Officer under the immediate supervision of Comdr. D.L. KAUFFMAN.

Lt. (jg) ROBBINS was placed in charge of developing the mapping, charting and photography department.

Ens. now Lt.(jg) JONES and Ens. now Lt.(jg) W.T. FLYNN were assigned as observers on the various recon and demolition maneuvers with specific duties to serve and report and recommend.

Ens. now Lt.(jg) PHELPS was assigned to the experimental department and laboratory under McALLISTER and with him his platoon to help in discovering solution to the problems immediately effecting demolition.

Ensigns now Lt.(jg)'s R. MILLNER, F. RAYMAN, M. WAKEFIELD, J. STEGMAIER, R. SPELLMAN, J. TURCI and Ch.Carp. R.F. WELLS were assigned the duties of personally training the new teams.

All of the above officers were given the necessary number of Team 7 enlisted personnel to help them in the instruction.

Teams 11, 12, 13, 14, 15, and 16 which reported at Maui during Team 7's sojourn there received their training at the hands of Team 7 personnel. When they were ready to pull out for their first encounter with the enemy they had been versed in as many tactics and strategies as Team 7 had encountered on it's operations, daylight reconnaissances, night reconnaissances, daylight demolition of both obstacles and coral and night demolition of both. They had seen what it was like to live aboard an APD and how important the making of neat and correct charts was, and how quickly bad communication procedure could result in confusion. They had been hounded with the fact that the beaches they were to come up against would be hostile and consequently swimmers should not stand upon the reef or splash about needlessly or get up onto the beach as they were doing in practice but the instructor knew that a few well directed bullets would do more convincing them than words.

At this time and during the teams' stay at Maui the personnel of Team 7 received a rather drastic change. It was here that Lt.(jg) ONDERDONK left this team and became C.O. of Team 14. Lt.(jg) ROBBINS then became executive officer and in his stead as Platoon Leader of Platoon 1, Lt.(jg) MILLNER became Platoon Leader.

Ensigns McWAKEFIELD and J.T. STEGMAIER left the team to become permanently attached to the base and as replacements Ensigns W. MARROW and A.W. HORTON were added to the team.

Chief Carp. WELLS left the team to become executive officer of Team 11 and later C.O. of that same team and Ens. D.J. WRYSINSKI was added as personnel officer. Lt.(jg) SCHANTZ left the team to become executive officer of Team 15 and Ens. now Lt.(jg) J.D. TURCI succeeded him as platoon leader of Platoon 4.

The team's officer organization then became as follows:

  • Commanding Officer - Lt. Comdr. R.F. BURKE
  • Executive Officer - Lt.(jg) S. ROBBINS
  • Personnel Officer - Ens. WRYSINSKI
  • Supply Officer - Lt.(jg) W.T. FLYNN
  • Platoon 1 -Ens. MILLNER, Ens. SPELLMAN
  • Platoon 2 -Lt.(jg) PHELPS, Ens. RAYMON
  • Platoon 3 -Lt.(jg) JONES, Ens. HORTON
  • Platoon 4 -Ens. TURCI, Ens. MORROW

So this well trained bunch of teams left Maui and Team 7 was regrouped and informed that Okinawa was in sight for it. So on 8 January a training program and reconditioning was imposed on Team 7 which continued until 14 February at which time it pulled away from Maui on board the U.S.S. HOPPING (APD 51) prepared to meet the Japs on Okinawa.

The immediate objective was Eniwetok where after a day's stay the HOPPING was ordered to join a small fleet of escort ships which would escort a convoy of merchant ships to Samar and Leyte Gulf where staging for the Okinawa Operation was intended, and where a rehearsal of the coming operation at Okinawa was performed.

OKINAWA OPERATION

For this operation the staging area was San Pedro Bay, Leyte, P.I. UDT 7 was there for 29 days during which, one rehearsal for the Okinawa operation was held. This took the form of a reconnaissance with some elements of the fire support group participating. The rest of the time here was spent aboard ship at anchor.

Underwater Demolition Team 7, embarked aboard the USS HOPPING, left Leyte Gulf, P.I. on 23 March 1945 for the objective, Okinawa Gunto. Plans were formulated for the reconnaissance of Yellow beaches on the western side of Okinawa Shima.

The reconnaissance, originally planned for LOVE minus 4 day (28 March 1945), was postponed for one day to enable the minesweepers to complete their mission. The sea was flat and calm, with negligible surf, and the swimmers approaching the beach faced the sun. The conditions provided little or no cover for the swimmers, and caused them to be easily seen in the water. Since the reconnaissance was made at high tide, the swimmers were enabled to remain well submerged at all times.

The plans provided for one pair of swimmers every hundred yards on a twelve hundred yard beach, to swim to the high water mark. In addition, four swimmers (making a total of 20 swimmers) were assigned to swim across the reef parallel to the beach. In ordere to have as few landing craft as possible approach the beach, on two were used to drop the swimmers in the water. One additional boat with the reserve swimmers was held in readiness 2000 yards from the beach. The primary fire support for this operation was provided by LCI(G)'s firing 40 MM shells at the beach, between the high water line and the dune line. This support was thoroughly backed up by destroyers, cruisers, battleships and air combat patrols.

Chronological order of events on 29 March 1945 are as follows:

0900 Landing craft lowered and loaded

0920 Landing craft headed for destroyer line (2500 yards from beach)

0930 Roger Hour - Boats crossed destroyer line. Reserve boat placed

Marine Corps observers and team officers aboard the LCI(G)'s.

0935 Boats 500 yards from beach; commenced dropping swimmers into water

0945 All swimmers in the water, and boats standing out to LCI(G) line (1000 yards from beach)

1045 Boats commence picking up swimmers who have returned from the beach.

1100 All swimmers recovered

1115 All observers recovered

1130 All landing craft and swimmers aboard USS HOPPING (APD 51).

A list of each man's assignment in the team for this operation is included at the end of this section also a chart of the beach reconnoitered.

The information brought back by the swimmers on these beaches was fairly comprehensive. It was found that LVT's and DUKW's could cross the reef, but that fissures in the reef would prevent landing craft from unloading tanks and other vehicles on the reef off Yellow 1, but on Yellow 2 both LST's and LCM's could unload with no difficulty. The reef was composed of hard live coral covered with sand and had a gradual slope. Only a couple of coral heads were found that would interfere with an amphibious operation. The beach was well defended with pill boxes and gun positions, but no opposition was encountered except for sporadic sniper fire.

Three rows of wooden posts, imbedded in the reef, were in place across Yellow 2 beach, approximately 40 yards from the high water mark. It was esti-mated that there were 200 of these posts (six feet high, averaging six inches in diameter) wedged into holes on the reef. From the amount of sea growth on the posts, it was apparent that they had been in the water some time. Although the team reported that they did not constitute an obstacle to assault waves mounted in LVT's, it was decided to return the following day and destroy them, in order to eliminate any possible hazard.

The following morning Platoon 2 carried out the mission of demolishing the posts. One Hagansen Pack or one 2 and one half pound block of tetrytol was required for each post. One hundred Hagansen Packs had been prepared by the team. These plus enough 2 and one half pound blocks for a hundred percent reserve supply of explosives, were made ready. The 2 and one half pound blocks were prepared in the following manner. All prima cord was cut free, and each block was reprimed with five tight wraps of prima cord held in place with friction tape. Old inner tubes were then cut into rubber bands, and one rubber band was secured to one end of each block. Thus the rubber band could be stretched around the post and looped over the end of the block; this caused the tetrytol to be secured firmly to the post. To permit the use of blocks on large posts, another rubber band was secured to the first to lengthen the stretch of the band, and the block was then used in the same manner as above.

Six Hagansen Packs or six reprimed tetrytol blocks were put into one havesack and secured therein. Each such pack was made bouyant by securing one marine jungle flotation bladder to the outside of the pack. Eight rolls of primacord were placed in a haversack and made bouyant in the same manner.

The plan called for eleven swimmers to transport explosives to the obstacles and two more to transport primacord. Three bouyant packs were secured together as a chain, and were dropped from the landing craft as each swimmer went into the water. Eleven swimmers each carried eighteen single block charges to the obstacles and commenced placing them and two other swimmers carried the primacord to tie in all charges to one firing load. A chronological order of events is as follows:

0900 Landing craft lowered and loaded

0920 Landing craft headed for destroyer line (2500 yards from beach)

0930 (1) One landing craft with swimmers and explosives headed for beach (2) Reserve boat placed observers aboard fire support ships

(3) Reserve boat with swimmers and powder remained 2000 yards from the beach

0940 Landing craft at reef edge; dropped swimmers and explosives

0950 All swimmers and explosives in the water. Landing craft underway 500 yards from beach.

1100 (1) All explosives placed and tied in.

(2) All swimmers recovered with the exception of two who remained to

detonate the charge at the firing signal.

1200 Fuzes pulled, and the remaining swimmers on way to boat.

1205 Swimmers recovered

1215 Charge detonated. 14 out of two hundred posts remained on beach.

This operation differed from the proceeding one in organization of personnel in that during the first operations, the swimmers were selected due to their experience and ability in the water. In the second Platoon Two went into the beach for the demolition work with Platoon Four as the standby. There was no opposition from the beach during all the time the men were in there. This was even more important than usual because the tide was receding while the men were working. When they first reached the posts, there was sufficient water for protection, but by the time they were ready to come back out it was only ankle deep. There was a delay in the firing time which meant that Lt.(jg) R.M. PHELPS and J.B. DAVIS, SF1c had to remain just a few yards off the enemy beach an extra half hour before pulling the fuzes. These two men spent their time, while waiting, counting the various enemy pillboxes and fortifications that were plainly visible from such a short distance.

The fire support plan for this operation was much the same as the preceding day. The deep support was presumably good but the close-in fire of 40 MM guns was in both cases erratic. One man, BRITTAIN, G.W. MM2c was wounded on the demolition operation as a result of a forty shell hitting a post near where he was working. All this fire which was supplied by LCI(G)'s, while very necessary, should be better controlled. On both operation numerous shells landed short of the beach and amongst the swimmers. A possible solution to this would be to have the LCI(G) firing line to move in to 750 yards or have the 40MM fire support done by destroyers using director fire and at a maximum range of 2000 yards. Another fault with the fire support was the lack of co-ordination between the ships and the team. There was considerable confusion when a request for fire on a particular area was made. However, the practice of having team officers aboard some of the fire support ships made up for this. This last is a great help because the C.O. of the ship gets a better picture of what's wanted in a much better position to spot any trouble and so correct it immediately.

Many of the swimmers were affected by the cold water and suffered severe cramps. Whenever possible, underwater demolition teams would be given the opportunity to become accustomed to cold weather and cold water swimming prior to an operation where such conditions are to be expected. Aluminum camouflage hoods and aluminum paint were practically of no value.

On 1 April 1945, Love Day, Lt. Comdr. BURKE went aboard SC 630 to be with the senior beachmaster. Lt.(jg) JONES went aboard the PC 1600 to aid the beachmaster of Yellow beaches while Ensigns RAYMAN and SPELLMAN with two men each went aboard control boats to assist guiding in the first two waves. On the afternoon of Love Day a reconnaissance was made of Yellow 3 beach by Ensign MORROW and 10 men of Platoon 4. Soundings were made of the river mouth and 200 yards on up the river. No demolition work was necessary except for several Sampans that partial obstructed the channel, but the beachmaster decided to leave them alone.

During the next four or five days a reconnaissance was made on White Baker 1, 2, & 3; Purple Baker 1, 2, & 3; and Brown Baker 1, 2, & 3. These beaches, all behind the front lines, were reconnoitered on order of Commander Task Force 51.19 in order to ascertain their usability for unloading supplies. The greatest difficulty experienced on these operations was in keeping the men from going up on the beach and looking for souvenirs.

On 7 April 1945 a reconnaissance was made of Red Baker 3 beach, Tsugon Shima, on the verbal order of Commander Group one, Amphibious Forces, Pacific Fleet (CTF 51.19) three days before the invasion of Tsugon Shima. Eight swimmers were used to reconnoiter the reef to the water line, and four more to cover the surrounding reef edge. Three landing craft were used on this operation - one to drop swimmers, another as a salvage boat, and another to carry reserve swimmers. The results of this are shown by enclosure (D5). No enemy fire was received at any time, and no casualties occurred. Two destroyers, the USS MORRISON and the USS LAWS, provided excellent covering fire while the swimmers were in the water.

Two days later, 9 April 1945, while aboard the USS HOPPING, UDT 7 suffered nine casualties with one man being killed. The APD had been on screening duty off Tsugon Shima two days previously and in even closer than this day. At approximately 1700 shore batteries from Tsugon Shima opened up and the ship sustained eight hits from estimated three and four point seven guns. Several of the shells went through the troop compartments which caused the casualties. Fortunately, the Japs used armor piercing projectiles, other-wise the ship would not have survived. One projectile passed over the overhead, making a long crease in it, up to which the tetrytol was stowed. The damage to the ship was slight but it necessitated it's return to Kerama Retto for temporary repairs. From here the APD, with the team aboard, proceeded down to Ulithi Atoll, Caroline Islands, in a five knot convoy.

After remaining at anchor in Ulithi several days, it was decided to put the team ashore and they were quartered on Asor Island. Five weeks were spent here during which time a natural channel was cleared and widened on 15 May 1945, west side of Hangejang Island. This was done to enable small boats to reach high water mark. The rest of the stay here was spent in wasting time. Each morning a half hour was devoted to P.T. and then there usually was a softball or volleyball game. The rest of the day was spent in trying to escape the heat. All the time demolition teams were on the island there was trouble with the island command. They discriminated between demolition personnel and base company to the extent that what few facilities were to be had on the island often were kept from them. Also an attempt was made to keep demolition officers from using the officer's club that was abortive.

Finally after too many days of sweating and shell hunting Team 7's orders for rehabilitation leave in the United States came through. A merchant marine transport, SS. JEAN LAFETTE, carried the team from Ulithi to Pearl Harbor. From there to Maui for a couple of days and then back to San Francisco on an APD, USS ATTALA. Here all members of the team were granted a thirty day leave expiring 11 August 1945 at Oceanside, California.

The Oceanside experience was a very bitter one for the older members of Team 7 as many teams with less time overseas and fewer operations to their credit had not only received their leave earlier but had had stateside duty as well at Ft. Pierce. All along promises had been made that Team 7 would get theirs. The original plan called for cold water conditioning here to last at least six weeks. Instead, a few hours after the return of most of the team, scuttlebut had it that the team was going out again to participate in the occupation of Japan. The ugly rumor seemed well founded when a large group of APD's were to be seen at anchor off the base.

Lieut. ROBBINS, C.O., relieving Lt. Comdr. BURKE who received a Chief of Staff job with one of the two Demolition Squadrons, was frantically questioned after he returned from each meeting with the powers. Finally, definite word came to load and the team minus most of their personal gear and little of the team gear went aboard the USS AUMAN ( APD 117). No sooner was everyone installed aboard ship when the first report came over the radio that Japan had accepted the Potsdam Terms for surrender. This naturally put everyone in a fine frame of mind for the trip. The next day much to everyone's dismay, the ship set out for Pearl Harbor, imminent peace not withstanding. It was an eighteen knot convoy of nine ships that left Oceanside for Pearl Harbor. Upon arrival in Pearl, boats were lowered and each one had an assignment to deliver and pick up various working parties assigned to pick up certain gear that would be needed in a demolition operation. The next day was the same helter skelter of working parties picking up the last of the gear which seemed to be scattered all over the harbor. We shoved off from Pearl Harbor almost exactly 24 hours after our arrival. There we said goodby to Lt.(jg) Bob PHELPS who was being discharged on the basis of the Silver Star Medal.

The trip to Eniwetok which was our next stop was uneventful except for the fact that we learned our ultimate destination - Tokyo Bay. The official word came as no surprise to the team. The stay at Eniwetok was much the same at Pearl. More gear to bring aboard with only eight hours to work. The last boat load of gear was brought aboard while we were underway heading out of the anchorage and for Japan. We left another officer at Eniwetok, Lt.(jg) Bill FLYNN, who was also being returned to inactive duty via the Silver Star route. The speed was still 18 knots and only three ships left in the convoy as the final lap of the trip got underway. There was much work to be done in the few days we had before reaching Tokyo Bay. All carbines, machine guns, and pistols were put in readiness for the coming operation. Blocks of tetrytol were attached with rubber bands and prima cord to be used as mine detonators and also to remove posts and other small obstacles. New type screws were installed on the landing craft to insure more speed. Radios were checked to make sure they were in proper working order. Everything was completed and the team was ready to carry out a demolition operation as it came into Tokyo Bay early in the morning on 4 September.

Scuttlebutt was running wild as to what the team was going to do. There was talk of clearing mine fields and obstacles, destroying small Japanese sui-cide boats and destroying the Japanese two man submarines that were said to be in hiding along the Japanese coast. But nothing happened and the feeling of unrest was very prominent among the members of the team. Also life aboard the AUMAN was not all roses as there was a mutual feeling of resentment between the ship's company and the team. The team seemed to be regarded as intruders on the ship and were often treated as such.

We lay at anchor in Tokyo Bay just off shore from Yokosuko, an industrial center just a few miles below Yokahama, for ten days. During these ten days the team engaged on occasional liberty in either Yokosuko or Yokahama. Liberty in Japan wasn't much to look forward to as there were no purchases to be made of articles worth carrying back to the ship. The civilians were always smiling characteristically at the Americans and seemed to be perfectly content that the war had ended. The cities were by no means clean and gave off a very revolting odor as did the natives.

On 14 September the team received orders to proceed north along the east coast of Honshu about 185 miles to Sundai and conduct a reconnaissance of the beach the next morning. The AUMAN shoved off from Tokyo Bay that evening. The boats and personnel gear was made ready during the trip. Platoon leaders were briefed and in turn briefed their platoons, giving each individual man instructions for carrying out his assignment.

Revielle the next morning was at 0545 at which time the ship had just reached a point of Yuriage beach which was the name given to the beach to be reconnoitered by Team 7. The plan of the day called for muster at 0720 at which time the gear lists were rechecked to see that everything was in order. The LCPR's were lowered into the water and brought alongside for loading the men and gear. After the loading, the boats made a quick radio check and every-thing was ready on schedule.

The boats started shoreward at full speed guided by the ship's radar toward the river which was the center of the beach. All guns were manned and in general all were prepared for any eventuality for there had been many rumors of resistance from the civilian population and several standing on the beach watching the operation. The swimmers were to be dropped in pairs each 100 yards in at least 25 feet of water and in no event closer than 100 yards to the beach. At about 200 yards from shore boats number 1 and 3 turned right and boats 2 and 4 turned left. The swimmers began hitting the water imme-diately after the turn was made. Each swimmer wore a face mask, swim fins, a sheath knife, and a plexi-glass slate with an outline of the beach marked on it and used for taking notes as to the depth of water, mines, obstacles during the reconnaissance. Rubber boats were used to cover the flanks of the beach due to the small number of swimmers available for the size of the beach. The rubber boats were equipped with outboard motors, carbines and lead lines to determine the exact depth of water. The boats were manned by one officer and two enlisted men. Buoys were dropped by the LCPR's to determine the flanks of the usable beach.

The water was very cold and murky, making it very disagreeable swimming and difficult to see under the water. Also the surf was very bad, making it difficult even for the landing craft and impossible for the rubber boats.

The reconnaissance was completed in about 45 minutes at which time all swimmers and rubber boats weer picked up. The C.O. then gave the word to send scouts ashore. Each platoon was to beach their landing craft and send ashore one officer and one enlisted man to look for exits and roads to be used by the incoming troops. Af first the scouts didn't know what to do about the Japs that were standing on the beach, not knowing whether they were hostile or not. When the scouts approached the Japs on the beach all fears were forgotten. The Japs were smiling and bowing. Most of them even wanted to shake hands and did before the scouting party was picked up. The land reconnaissance only took about 30 minutes as there was very little of importance on the beach. The C.O. again passed the word for the landing craft to beach and the scouting parties were picked up and the team headed back for the ship with all necessary infor-mation.

Upon arrival at the ship interrogation of swimmers, rubber boat crews, and scouting parties was held immediately. A rough chart showing all informa-tion that was obtained was drawn up that morning. Demolition work was scheduled to take place that afternoon but none was necessary. That afternoon was taken up by preparing the dispatch and the final detailed chart of the beach. This was completed by mid-afternoon and was delivered to the C.T.G. 32.2 by the team C.O. The chart and dispatch were accepted as very complete and satisfactory. Early next morning the team was on its way to Tokyo Bay.

We no more than reached Tokyo Bay than we found ourselves in the midst of a typhoon. However, the bay afforded protection and took the fierceness out of the storm. Practically every ship in the bay was blown away from it's original anchorage but no real damage was done. The next few days in Tokyo Bay was taken up with liberty and wild stories about immediate discharge for Underwater Demolition Team members. We shoved off from Tokyo Bay on 21 September homeward bound.

The first stop was Guam where the team spent three and a half days mostly taken up with loading the ship with excess demolition gear and powder to be taken back to the states. The ship was loaded to capacity and the team shoved off again for Eniwetok. This stop was only a few hours, which was taken up with refueling and the team was off again, this time for Pearl Harbor where the team spent two days and two liberties and then off again. This time it was the final lap to San Diego, California.

Upon arrival at San Diego, 13 October 1945, the team was immediately sent over to the Amphibious Training Base at Coronado where the post-war demolition was to make its headquarters. All members of the team thought that here at last was UDT 7's opportunity for some stateside duty. Everyone thought that the teams would remain there for a month or so and then gradually decom-mission. Instead the rather intangible process of decommissioning was started on Monday morning. This consisted mainly of paper work and signing over the gear.

The men not eligible for discharge were transferred to ATB for further assignment by Commander Western Sea Frontier. The officers not eligible for discharge were made available to BuPers for reassignment. Team 7 officially went out of existence on 27 October 1945, the same morning that men and officers who were on the Marianas operation received their medals.

Though demolition was a war baby, the officers and men of Team 7 were veterans in every sense of the word. From the start on Saipan to the finish of combat at Tsugan Shima a high brand of courage and fine work was displayed at all times. Probably the most noteworthy thing about demolition as a whole was the splendid group of officers and men assembled together.

CHRONOLOGICAL LIST OF TRAINING PERIODS, MOVEMEMTS AND OPERATIONS OF UDT # 7

JANUARY 1944 - FEBRUARY 1944: Majority of enlisted men trained together at Camp Peary, Virginia.

MARCH 1944 - 9 APRIL 1944: Trained at Fort Pierce, Florida as individual Naval Combat Demolition Units as members of Class 5 and 5A.

21 APRIL 1944 - 30 MAY 1944: Formed UDT 7 and had further training.

12 JUNE 1944: Reconnaissance made of Yellow and Blue beaches on Saipan Island.

15 JUNE 1944: Post-assault work done from D-Day to D plus 5 consisting of buoying channels and blasting work done at request of beachmaster.

23 JULY 1944: Reconnaissance of Red, Green, and Blue beaches, Tinian Island.

24 JULY 1944: Post-assault work commenced on D-Day and lasted till D plus 2. the work consisted of searching for anti-boat mines on fringing reef off White 1 and 2 beaches and aiding in placing pontoons on these beaches.

AUGUST 1944: Turner City, Florida Islands. 11 days ashore for reconditioning.

12 SEPTEMBER 1944: White beaches, Pelelieu, Palau, were reconnoitered.

15 SEPTEMBER 1944: Post-assault work done under orders of beachmaster from D- Day to D plus 6. Work consisting of placing anchorage buoys and clearing mines and obstacles from Orange, Scarlet, and Purple beaches.

1 OCTOBER 1944: Fire of explosive loaded on deck of USS STRINGHAM (APD 6) in Manus anchorage.

16 OCTOBER 1944 - 14 FEBRUARY 1945: Maui participated in training of new teams and received a month of additional training and conditioning.

23 FEBRUARY 1945 - 15 MARCH 1945: San Pedro anchorage Letye, staging area and one practice reconnaissance.

MARCH 1945: Reconnaissance made of Yellow beaches on Okinawa Shima.

MARCH 1945: Demolition work clearing of wooden posts on Yellow 2 beach.

1 APRIL 1945: Post assault work done on D-Day to D plus 5 with Yellow 3 beach reconnoitered and beaches White Baker 1, 2, & 3; Purple Baker 1, 2, & 3; Brown Baker 1, 2, & 3. These last named group of beaches were behind enemy lines and were reconnoitered to ascertain their usability for unloading supplies.

7 APRIL 1945: Reconnaissance made of Red Baker 3 beach, Tsugon Shima.

9 APRIL 1945: Casualties suffered aboard USS HOPPING (APD 51) when hit by shore battery fire from Tsugon Shima.

1 MAY 1945 - 9 JUNE 1945: Based on Ulithi Atoll, Caroline Islands for reha- bilitation.

JULY 1945: Returned to states for thirty days leave.

15 AUGUST 1945: Boarded ship from Oceanside, California for occupation of Japan. At anchor Tokyo Bay.

14 SEPTEMBER 1945: Reconnaissance of Urarigi Beaches near Sendai, Honshu Island.

13 OCTOBER 1945: Returned to A.T.B. Coronado, California.

20 OCTOBER 1945: UDT #7 decommissioned.

(compiled by Robert Allan King for the UDT-SEAL Museum from public records at the Operational Archives of the Naval Historical Center)

TEAM ROSTERS - To protect the integrity of the Teams and the privacy of individual frogmen, Team rosters are not made public. If you or your relative was a member of UDT Team SEVEN and you would like further information, we suggest you contact the UDT-SEAL Museum.

 NSWA home